Development mock 4 rows, not live records · Compare verified work against the current programme. Source: Estate (development backend) (not connected) · Connect Estate (development backend) to create records · Planned: JV-103

100% / 100%Raft foundationCompleted
60% / 52%Slab pour on 18 Nov 2026In progress
35% / 38%Typical floor cycle 6In progress
0% / 0%Mock-up flat approvalPlanned

Showing 4 of 4 rows